Name of Proposal: 10th Street Improvement Project.

Proponent: City of Gold Bar

Description: The proposed project consists of the construction of curb, gutter, sidewalk, ADA-compliant curb ramps, water main replacement, and storm drainage improvements along the west and east sides of 10th Street from State Route 2 to the water meter vault located on Glacier Place.

Location: The project is situated within the SE ¼ of Section 6, Township 27N., Range 9 E W.M. The project is located within the 10th Street Right-Of-Way between State Route 2 and the Meter Vault located on Glacier Place. (Site map attached)

Lead Agency: City of Gold Bar

Threshold Determination:
The lead agency for this proposal has determined that the project does not have a probable significant adverse impact on the environment. An environmental impact statement (EIS) is not required under RCW 43.21C.030 (2)(c). This decision was made after review of a completed environmental checklist and other information on file with the lead agency. This information is available to the public on request.

 Comments and Appeals:
This DNS is issued under WAC 197-11-340(2); the lead agency will not act on this proposal for 14 days from the date below.

Any interested party may submit written comments on this determination. The City of Gold Bar must receive written comments or appeals before 5:00 PM on Thursday, May 18, 2017. Any appeal shall state with specificity the reason why the determination should be revised. Comments should be addressed to the responsible official designated below.

Responsible Official: John Light
Public Works Director
107 5th Street
Gold Bar WA 98251
360-793-1101

 

To view signed DNS click here!

To view Sepa Environmental Checklist click here!